Pre-Pour Checklist

  1. Clear area, as close as possible to building, in a central location, big enough for two semi trailers and several truckloads of sand (truckloads depends on job size).

  2. Building must be maintained at a temperature above 50 degrees long enough before pour so that the subfloor, ambient temperature and humidity can stabilize.

  3. Installation should be after drywall and taping are completed.  This is very important to eliminate horizontal sound leaks under the drywall and to prevent excessive construction traffic which could result in floor damage.

  4. Subfloor must be broom-clean and free of mud, oil, woodchips and/or contaminates.  Cut all plastic on exterior walls.

  5. A 15 GPM water supply must be available within 300 ft. using a minimum of two 3/4 I.D. faucets.

  6. Remove any bottom plates that go through doorways and install bulkheads at all stairways and doors.

  7. Bulkhead off areas where FIRM-FILL does not get poured.

  8. Stool collars raised and bathtubs shimmed up.  Plumbing chases sealed up if FIRM-FILL is required under tubs.  Drains taped off.

  9. All structural holes in subfloors must be covered and plugged, also delaminations repaired.